- Installed new branch circuitry from existing panel location
- Added conduit raceways and wire for new ASRS being installed
- Provided and installed a new ATS and extended the feeder for the ATS to the existing generator
- Demoed, made safe, and installed new lighting w/occ sensors and wall switches
- Swapped out distribution in (2) separate locations in the facility. This was accomplished in less than a week. All while maintaining normal operations of the DC by utilizing generator power to temporarily feed the distribution panels and facilitating no loss in operation for the customer.